NAVAL, Biliran – The construction of the new Caray-Caray bridge will start tomorrow, August 30, 2019.
Contractor: JFAP Construction/L.M. Baltonado Construction (JV)
Date Started: August 30, 2019
Contract Completion Date: March 11, 2021
Contract Cost: CY 2019 – Php 68,783,780.00
CY 2020 – Php 87,755,540.84
TOTAL PHP 156,539,320.84
Implementing Office/Contact No.: DPWH RO8
Source Fund: GAA 2019 & 2020

– BiliranIsland.com